
July 2010
Government Lift
Station Generator
Fuel Tanks |

July 2010
Government Lift
Station MCC Rooms |

January 2010
Moreno Rd. Lift
Station Generator
Odor Control Slabs |

January 2010
Moreno Rd. Lift
Station Generator 2 |

January 2010
Moreno Rd. Lift
Station Generator 1 |

January 2010
Pipeline Rd. Lift Station
Pumps 3 & 4 |

January 2010
Pipeline Rd. Lift Station
Chopper Pumps |

January 2010
Pipeline Rd. Lift Station
24x30 Reducer Install |

December 2009
Moreno
Lift Station
Valve Vault |

December 2009
Moreno
Lift Station
Pig Launch Install |

December 2009
Moreno
Lift Station
Electrical Bldg. Slab |

December 2009
Government Street
Lift Station Hatches |

December 2009
Government Street
Lift Station
Colored Launch Install |

December 2009
Government Street
Lift Station
Shoring |

November 2009
Government Street
Lift Station
CMU Work |

November 2009
Government Street
Lift Station
Column Form Work |

November 2009
Government Street
Lift Station
Column Rebar |

November 2009
Rainbow Ave. (LS A)
Pump Room Walkway II |

November 2009
Rainbow Ave. (LS A)
Pump Room Walkway |

November 2009
Lift Station B
Retaining Wall |

November 2009
Lift Station B
Manhole #10 |

November 2009
Lift Station B
Valve Vault |

October 2009
Lift Station B
Wall Rebar III |

October 2009
Lift Station B
Wall Rebar II |

October 2009
Lift Station B
Wall Rebar I |

September 2009
Rainbow Ave
Pump Room Piping |

September 2009
Rainbow Ave
Surge Relief Valves |

September 2009
Lift Station 186
Transmission Main
Reynolds Installing |

September 2009
Lift Station 186
Transmission Main
Installation |

September 2009
List Station B
Wall Forms Complete |

September 2009
List Station B
Wall Forms Being
Constructed |

September 2009
List Station B
SST Wall Pipes
Form Valve Vault |

September 2009
Government St.
Upper Bldg Forms |

September 2009
Government St.
Rebar Installation |

August 2009
Government St.
Pipeline Construction |

August 2009
Government St.
Pipeline Construction |

August 2009
Government St.
Lift Station
Construction |

August 2009
Government St.
Lift Station
Construction |

August 2009
Lift Station A
Electrical Room |

August 2009
Lift Station A
Variable Frequency
Drive |

August 2009
Government Street
Lift Station |

August 2009
Government St Lift
Station Hatch
Installation |

August 2009
Government St Lift
Station Forcemain
Installation |

August 2009
Lift Station B
Wetwell Aerials |

August 2009
Lift Station B
Wetwell Liner |

August 2009
Government Street
Lift Station |

August 2009
Government Street
Lift Station |

August 2009
Government Street
Lift Station |

July 2009
Lift Station A
On-Site Generators |

June 2009
Completed Crom Tank
at Lift Station A
|

June 2009
Lift Station A
Discharge Headers |

May 2009
First Lift Form
Install Government St. |

May 2009
Lift Station A
Surge Relief Valve |

May 2009
Lift Station A
Building |

May 2009
First Lift Rebar
Install Government St. I |

May 2009
Base Slab Form Install
Lift Station B |

April 2009
Excavation at
Lift Station B |

April 2009
Base Slab Rebar
Install Government St. |

April 2009
Lift Station A
Odor Control Units |

April 2009
Lift Station A
Knife Gate Valves |

April 2009
Base Slab Finish
Government Street |

April 2009
Government St.
Lift Station
Concrete Pour 3 |

April 2009
Government St.
Lift Station
Concrete Pour 2 |

April 2009
Government St.
Lift Station
Concrete Pour 1 |

March 2009
Deep Well Install
Lift Station B |

March 2009
Government St. Lift
Station Site
Preparation |

March 2009
Lift Station A
Tank Installation |

March 2009
Lift Station A
Brick Installation |

February 2009
Government St
Lift Station
Sheet Piling |

February 2009
Government St
Lift Station
Sheet Piling |

February 2009
Installing Deep Wells
at Government Street
Lift Station |

January 2009
Work Begins at
Government St. Lift Station |

January 2009
Installing Sheet Piling
at Government St. Lift Station |

January 2009
Installing Sheet Piling
at Government St. Lift Station |
 November 2008
Rainbow Ave
Lift Station |

November 2008
Rainbow Ave
Lift Station |

November 2008
Rainbow Ave
Lift Station |

September 2008
Rainbow Ave
Site Clearing |
 September 2008
Rainbow Ave
Site Clearing |
 September 2008
Rainbow Ave
Land Clearing |
*Under Florida law, e-mail addresses are public records. If you do not want your e-mail address released in response to a public-records request, do not send electronic mail to this entity. Instead, contact this office by phone or in writing.